TRAFFIC PATTERN CHANGES:

  • Existing Route CC and Rifle Range Road CLOSED for tie ins to new Route CC on October 12
  • Marshall Road, east roundabout and new Route CC OPEN to traffic as of October 12

Work Scheduled:

  • Interchange
    • Pouring concrete for curb and sidewalk at west roundabout along new Route CC
    • Installing street lighting at east and west roundabouts of new Route CC
    • Pouring concrete for bridge approaches and barrier wall of new Route CC bridge over I-44
  • Traffic Impacts:
    • ROAD CLOSED: Existing Route CC and Rifle Range Road CLOSED October 12 until late-October
    • Drivers urged to find alternate routes
    • Nighttime lane closings on I-44 at Mile Marker 103 possible at times. Work hours: 8 p.m. to 6 a.m.
    • Drivers should not pass in the work zone due to the narrowed driving lanes on I-44 at Mile Marker 103
    • I-44 speed limit reduced to 60 mph at times
    • Crews and equipment close to traffic in areas

(Weather and constructions delays could alter the work schedule.)

Project Summary:

  • Interchange:
    • Build a new bridge to take Webster County Route CC over I-44 at Mile Marker 103
    • Relocate Webster County Route CC at Rifle Range Road to intersect with I-44
    • Build interchange ramps so drivers safely exit and enter I-44 at Webster County Route CC
    • Build roundabouts at either end of interchange to connect with Brinkley Road/I-44 out road on the west and Marshall Road/Route CC on the east
    • Prime Contractor: H.R. Quadri Contractors, LLC of Van Buren
    • Completion Date: June 2021. However, the interchange will open to traffic by December 31, 2020
    • Total Project Cost: $16.4 million
  • Roundabout:
    • Build a roundabout at the intersection of Hubble Drive, Buffalo Street and Banning Street
    • Install new street lights at roundabout
    • Resurface Hubble Drive between Rifle Range Road and Spur Drive (Route 38) in Marshfield
    • Route CC between Rifle Range Road and Route 38 in Marshfield turned over to the city of Marshfield after completion of the interchange project
    • Prime Contractor: APAC-Central, Springfield
    • Completion Date: December 2020
    • Total Project Cost: $1.9 million

 

 

(For more information, call MoDOT in Springfield at 417-895-7600 or visit www.modot.org/southwest)

(Follow MoDOT’s Southwest District: Facebook | Twitter | Instagram |YouTube)

(Take the Challenge! Buckle Up/Phone Down)



Source link

Author: Editor
Editor represents multiple online news sites, including STL.News, RSSNews.Press and more. As a media company offering website hosting, design and SEO we create the news sites in part to illustrate our "search engine friendly" web hosting and design services. In addition, we believe that our "direct source news" concept helps provide accurate information to the public without bias.