No traffic impacts expected from noon Wednesday, November 25, until 9 a.m. Monday, November 30, during the Thanksgiving Holiday weekend.

Work Scheduled:  

  • Striping Route 160 between I-44 in Springfield and Route AB in Willard
  • Laying seed and mulch on Route 160 between Hunt Road/Farm Road 103 and I-44 in Springfield
  • Pouring concrete islands, grading and moving rock/dirt at Farm Road 94 roundabout
  • Grading and moving rock/dirt near new sidewalk at Route 160 and Hunt Road/Farm Road 103
  • Installing road signs in areas

Traffic Impacts:  

  • Traffic to one lane in each direction on Route 160 in the eastbound and westbound lanes between Hunt Road/Farm Road 103 and I-44 in Springfield
  • All lanes open in each direction on Route 160 between Hunt Road/Farm Road 103 and Jackson Street
  • Frisco Highline Trail OPEN at Hunt Road/Farm Road 103
  • New roundabouts on Route 160 at Jackson Street, Hunt Road/Farm Road 103, and Farm Road 94
  • New J-Turn on Route 160 at Farm Road 123/Westgate Avenue
  • Right-in/Right-out at Haseltine Road (Farm Road 115)
  • Equipment crossing county farm roads at times. Short-term traffic stops by flaggers to allow equipment to cross the road.
  • Crews and equipment close to traffic
  • Crews may work Saturdays and Sundays to make up work missed due to weather/construction delays

(Weather or construction delays could alter the work schedule.)

Project Summary:

  • Widen Route 160 to four lanes between I-44 in Springfield and Jackson Street in Willard
  • Resurface the existing lanes of Route 160 between I-44 in Springfield and Route AB in Willard
  • Install concrete traffic barrier between lanes in areas
  • Add a pedestrian underpass underneath Route 160 at Hunt Road
  • Add a new box culvert to carry Frisco Highline Trail underneath Route 160 at Trail Mile 3
  • Add street lighting at intersections
  • Intersection improvements:
    • J-turn at Farm Road 123/Westgate Avenue
    • Right-in/Right-out at Haseltine Road (Farm Road 115)
    • Roundabout at Farm Road 94 near quarry
    • Add left-turn lane at Hughes Road
    • Roundabout at Farm Road 103/Melville Road/Hunt Road
    • Roundabout at Jackson Street
    • Add turn lanes at Greene County Route AB
  • Prime Contractor: APAC-Central, Springfield
  • Completion Date: December 1, 2020
  • Total Project Cost: $18.6 million 

END 

(For more information, call MoDOT in Springfield at 417-895-7600 or visit www.modot.org/southwest

(Follow MoDOT’s Southwest District: Facebook | Twitter | Instagram |YouTube)

(For timely traffic information in the Springfield area, visit www.ozarkstraffic.com) 

(Take the Challenge! Buckle Up/Phone Down)



Source link

Author: Editor
Editor represents multiple online news sites, including STL.News, RSSNews.Press and more. As a media company offering website hosting, design and SEO we create the news sites in part to illustrate our "search engine friendly" web hosting and design services. In addition, we believe that our "direct source news" concept helps provide accurate information to the public without bias.